Gas Detection Supplier - Hazard Area Gas Detection installation
- Electrical Haz installation of a Gas Detection system as to Clients drawings and spec. (18units)
- Location - Gold Coast
- Project Valve $45,000
- March 2013 (2 weeks)
Major Crane supplier - Installation of 6 Cranes at the Port of Brisbane
- Installation / Commissioning of system
- Supply of 6 electricians & 4 Mechanical fitters & 2 Labours to complete the installation
- Control wiring / Motor cabling / Construction
- Project management of the whole project from start to finish. Turn key solution
- Nov 2012 to March 2013 - 6 month Project
Gathercole Project – Controls installation
- Electrical Design & installation of new valves / pe’s
- Inputs and outputs to control the new upgrade
- MCC Construction
- Installation of cabling to the field I/o and valves
- Motors (VSD)
- Electrical Design installation / Commissioning of the system
- Electrical drawings of completed project
- Oct 2012 / 2month Project
- Project $120,000
World Leading Materials Handling Supplier - Conveyor installation
- Electrical installation of the conveyor system as to Clients drawings and spec.
- August 2012 to Jan 2013
- Location - Perth (Western Australia)
- Project Valve $400,000
World Leading Materials Handling Supplier - Conveyor installation
- Electrical installation of the conveyor system as to Clients drawings and spec.
- Sept 2012 to Oct 2013
- Location - Brisbane (Airport - Australia AirExpress)
- Project Valve $120,000
Major Cabling Company - Design & installation of 2000amp Main supply & Submain installation over 200mtrs at roof level.
- Design/ Installation / Commissioning of system / HV & LV
- Supply of 2000amp Main Switchboard / Motor control Board
- Cable ladder installation to feed all motors
- Control wiring / Motor cabling
- Project management of the whole project from start to finish. Turn key solution
- August 2012 to Dec 2012 - 5 month Project
- Project $1,200,000
Major Storage Company – QLD Service / Maintenance Contract
- Electrical / Mechanical installation of Systems
- Routine serving all year round All over Qld
- We stand by our clients’ product
- Take own ship of the Contract for Queensland
- From 2008 – still on going. (Call the office to find out more)
- Estimated - $200,000 / Pa
Project Management Company – Upgrade of Oil Tank System
- Electrical Design & installation of new valves
- Inputs and outputs to control the new upgrade
- MCC additions and changes
- Installation of cabling to the field I/o and valves
- Motors
- Major changes to MCC were completed out of hours to meet
production times and process of the installation
- Upgrade
- Electrical Design
- Installation
- Commissioning of system
- Electrical drawings of completed project
- Nov 2011 – Jan 2012 / 3month Project
- Project $70,000
Automation Installation - Support Main contractor in the installation of Robots & Design of integrating the system from Old to New
- 8 Pallet Robot installation and conveyor system
- Redesigning the old conveyor system to hand the new layout
for the robots and reprogramming and building a system to control that.
- Design/Programming I/O wiring and install
- Commissioning of system
- 6 month Project 2011
- Project $800,000
Leading Process Technical Solutions Company - Automation Installation
- Electrical installation of a new Milk plant upgrade
- I/o wiring and install / commissioning of system.
- 2011 - 3 month Project
- Project $200,000
Major Fast Food Retailer - Store Rollout (Qld & North NSW)
- Electrical installation of New screens and general power to selected areas. (approx 165 stores)
- Works on going 2010 - 2012
- Project Approx $1,300,000 plus
Metropolitan Water Provider – Leakage & Pressure Management Program
- Approx – 40 PRV / PV have been completed to date
- Install & Commissioning of PRV / PV pits around Brisbane ( As to a program set by the client)
- Component installation / Electrical connection to energex / Commissioning & Testing / Reports
- Aug 2008 – Dec 2011
- Project Valve $1,000,000 approx.
World Leading Materials Handling Supplier - Conveyor installation
- Electrical installation of the conveyor system as to Dematic's drawings and spec.
- Contact: - Andrew Jones (Project Manager)
- July- August 2009
- Project Valve $190,000
World Leading Materials Handling Supplier – 2011 Conveyor Installation
- Electrical installation of the conveyor system as to Dematic's drawings and spec.
- Contact: - Andrew Jones (Project Manager)
- August 2009 to March 2010
- Project value $550,000
Procast – Warehouse 2 – Industrial Electrical Installation
- Full installation of General light and power
- Sub Mains and 1200amp Main Switchboard of new build
- Including Crane points, Dynalite controls, IP56 1 & 3phase outlets.
- Contact: - Procast, Andrew
- 2009 – 2010
- Project value $780,000
Kilcoy Project - Design & Construct & Install / PLC control project
- Electrical Design – Schematics, Layouts
- Built Motor control Cabinet
- Onsite installation ( 2 week on site install)
- PLC Programming of the system, On site commissioning (Most of the commissioning will be done before the install)
- Completed 7th July 2009
Conveyor Install - Designed & Installed
- Automation of a conveyor system
- Electrical design and installation of the complete conveyor system.
- Scope of works - Emergency stop circuits, Motor cabling, Prox & PE wiring of the system.
- Project Valve - $ 80,000 ( 3 weeks )
Ultrasonics MCC - Design & Construct
- Design & Construct MCC
- 2000 litre Tank.
- Scope of works - Design, Drawings, Build electrical cabinet, Tested in K & L's workshop before sent to PNG.
Electrical Industrial Install - General Light & Power
- Industrial Install
- General Light & power install.
- Cable ladder, XLPE's Submains, sub circuits.
- Project Valve - $ 750,000 ( 3 months )
Railway - Carpark Lighting Installation
- The project included the following works.
- Electrical & Communication Conduits / Pits.
- Installation of 18 street light poles & lights and testing and commissioning of the lighting system.